Shiftplanning - How to best use workgroups and teams

I want to start using Shift Planning in CM but I am still struggling how to best utilize the workgroups and teams.

Example:

I have in one Team multiple Production lines where I need a machine setter and multiple operators. This team needs one shift leader.

What is now the best way to set up the workgroups and teams?

Any ideas?

Much appreciated. Let´s see what the CM Community can :slight_smile:

BR Michael

Let´s see if I can get new attention to this post :slight_smile: after the new launch of the Community

Hello Michael.

Some questions before I can give you a good answer.

  • How did you model the Production Line in your MES? As Areas, as resources, as line, as ..

  • Is the machine Setter an additional role who will setting up machines for a production run, changing tools, etc..?

  • Are you using the Certification functionality in your MES?

Thanks

Hi Jose,

  • Production Lines are Parent-Resources, with the Stations as Sub-Resources
  • Correct, Machine Setters is responsible to ensure the machine is running, material is available etc. Fun part is that each person can work on different lines in different roles. So I can be a machine setter on Line A but I am only an operator on Line B. Same applies to shifts. I might work this week in a morning shift but next week I do a late shift. This is my main problem with the shiftplanning in CM as it SEEMS that you only can have one Home workplace/team/shift and everything else needs to be manually overwritten. That´s why I issued this post.
  • Yes we are tracking on each blue collar the certifications for Operators and Setters for each line separately as a cerification but so far completely separate/detached from shift planning.

Hi Michael!
I’m still getting familiar with your scenario, so apologies in advance if I’ve misread anything :sweat_smile:

Rotating shifts; In CM, employees are linked to a Team rather than to a fixed shift, and the Calendar decides which Team works each shift on each day. This is done through the Team Pattern in the Shift Definition. For example, with a 3-shift definition (Morning 06-14, Afternoon 14-22, Night 22-06) and Teams A, B and C:

  • Morning: ABC
  • Afternoon: CAB
  • Night: BCA

Each working day the pattern moves one position, so a Team goes Morning > Afternoon > Night. For a weekly rotation like yours, repeat each code once per working day (e.g., AAAAAAABBBBBBBCCCCCCC for Mon-Fri). This way nobody needs to be moved manually week by week. Shift codes and colors make it easy to see who is on which shift each day.

Now for the scenario of different roles on different lines - each employee has one home Team/Workgroup/Position. Assign the role they perform most often, then use Assign Employee Temporarily when they cover another role or line. The Availability Pool flags people who can be moved.

Hope this helps!

Hello Michael,

Sorry for the delay.

Regarding your scenario, the main challenge lies in the fact that an employee can be a “regular” operator on one production line and a Machine Setter on another. And I asked whether you were using certifications because, without them, shift plan management is practically non-existent.

To explain how to manage a Shift Plan, let’s consider the following scenario:

  • Working from Monday until Friday, 24 hours a day, with three Teams. The teams rotate between the different shifts on a weekly basis

  1. You need first to create the Teams

image

  1. Create the Shift definition fir the calendar and set the ShiftDefinitionShift.

  • 2 Lines

Line A with 1 Resource and stations

Line B with 1 Resource and stations

  • Certifications

A global Certification for Regular Operators (Certification “Operator”)

A Certification for Team Leaders (Certification “Team Leader”)

A Set of different Certification for the Machine Setters (In this case because we have 2 Lines: Certifications “Machine Setter LINE A” and “Machine Setter LINE B”

Manage the Certifications to the operators

  • Having that set you can now create the ShiftPlan and Workgroup (1 Workgroup per Line)
  1. For each Workgroup define the Resource(s), optionally the Step(s) and more important the positions needed. In this example for the Line A you will need 4 operators, 1 Team-Leader and 1 Machine Setter for this specific Line (This is where the Certifications play a role)

2.

  1. For every Workgroup manage the Teams (Use Special Manage Shift if your employee is not the Manager of the other employees)

Easier to be done with Master Data

  1. Having that done you can see the Summary by Line (Workgroup) and Team

  1. Now Manage the Employees

Here you have several options

  • Add Non Working day time
  • Remove Non-Working Day/Times
  • Add Work Availability
  • Remove Work Availability
  • Temporary Assignment
  • Place in pool
  • Remove from Pool
  • Remove Temporary Assignment

Let me know if you have any additional question. If you want I can share the MasterData I created for this example

See you

Romeu

Hi Michael,

I would separate the crew organization, the staffing requirements of each production line, and the qualifications needed to fill each position.

Use Teams to represent the crews that rotate between shifts
A Team does not need to correspond to a single production line: its Employees can fill positions in different Workgroups.

Use Workgroups to represent the production lines needing staffing. For example:

  • Line A Workgroup: one LineSetter and the required number of LineOperators.
  • Line B Workgroup: one LineSetterand the required number of LineOperators.

Associate the relevant Resources with each Workgroup. A Resource should only be associated once across the Workgroups of the same Shift Plan.

Use the existing Certifications as the planning positions

Your line-specific Certifications are useful here. In Workgroup Personnel Requirements, a Position corresponds to a Certification.
An Employee could hold both LineSetter and LineOperator Certifications. Their normal assignment could be Setter in the Line A Workgroup, with a temporary assignment to Operator in Line B when needed. The temporary-assignment operation checks that the Employee holds a valid Certification for the destination Position.

Handle the shared shift leader explicitly

One leader covering several lines should not automatically become one leader requirement per line.
A possible approach to investigate, is a separate leadership Workgroup, with one Shift Leader position, alongside the line Workgroups.

I would validate that configuration in your MES version before recommending it, particularly how it represents shared coverage.
Also clarify whether the leader is dedicated to supervision or is expected to fill an operator/setter position simultaneously. Those represent different staffing requirements.

Use Team Patterns for the rotation between shifts

The Calendar determines which Team works each shift on each day. Employees therefore do not need to be reassigned manually just because their Team moves from the morning shift to the afternoon shift.

  • Use temporary assignments for changes between lines or positions.
  • Placing an Employee in the pool indicates that the working Employee is offered for reassignment.
  • Setting work availability indicates that an off-duty Employee is available to work.
  • Neither action changes the assignment: the Employee still needs to be temporarily assigned to the desired Team, Workgroup, and Position.

The frequency of those changes matters.
Team Patterns handle shift rotation, but they do not decide which Employee should work on which line or in which position.

For example, if someone normally works as Setter on Line A but needs to work as Operator on Line B tomorrow, that change needs to be recorded. If this happens occasionally, temporary assignments provide a clear way to handle it.

How often do your Employees change line or position, and are those changes planned in advance or decided during the shift? That would help determine whether temporary assignments are manageable or whether your main requirement needs further investigation.